A large-scale project that has been completed by our team in less than 3 months and includes:
– Complete rehabilitation of a BB5 water injection pump,
– Complete rehabilitation of a 1-storey multiplier, API 613,
– Refurbishing pump, multiplier and electric motor installation plans by resining
– Setting up each unit on the skid
– Installation and connections of auxiliary equipment
– Pump/reducing/motor train line
– Group commissioning and monitoring of operating parameters